The new plant sits next to your customer’s assembly plant. The building is ready, the moved machines arrive next month, and the old line stops when the new one is approved. You have the mother plant’s PFMEA, a list of new equipment and a hiring plan. The customer’s supplier quality engineer wants to know what changes and when the PPAP comes.
This guide is for the launch or quality lead moving production to a new plant, or adding a 2nd plant for the same parts. It covers the requirements for a site change, the PFMEA, the control plan and gauges, the PPAP plan and what to tell the customer.
The short version
- Tell the customer before anything moves. Get the approval route, the PPAP level and the elements in writing.
- Adapt the mother plant’s PFMEA. Copying misses what changed. Starting over loses what the mother plant learned.
- Put the mother plant’s 8Ds, complaints and scrap causes into the new PFMEA before trial runs start.
- Keep the old line able to run until the new site is approved.
What the Customer and the Standards Require
Notify the customer before the move, get its route in writing and plan a new approval from the new site. The rules sit in 4 places:
- PPAP. The AIAG PPAP manual lists “production from tooling and equipment transferred to a different plant site or from an additional plant site” among the changes that need customer notification. Expect a new PPAP from the new site before it ships production parts, at Level 3 unless the customer sets another.
- IATF 16949. Clause 8.5.6.1 names a change of manufacturing location among the changes that should require a production trial run. When the customer requires it, you also notify it and get documented approval before the change. The clause does not separate temporary from permanent moves (clause text).
- Your certificate. Under the IATF Rules 6th edition, in force since January 1, 2025, you notify your certification body of any relocation. The body decides between an initial audit at the new location, a special audit or added time at the next audit (DNV summary).
- VDA 2 for German customers. The 7th edition (January 2026) defines relocation as a complete or partial change of the location of production. A product made at different sites, on different equipment or processes, needs a separate approval procedure for each, unless agreed otherwise.
Customer rules differ. Get the route, the level and the elements in writing.
What Changes at the New Site
The part stays the same. Almost everything that makes it changes. Walk every operation through 6 headings:
- Equipment. New machines, or moved machines on new foundations with new utilities and new settings.
- People. New operators, setters and inspectors. What the mother plant’s team knows but never wrote down stays behind.
- Environment. Temperature, humidity, dust and vibration.
- Material and suppliers. Local sources for material, components or services such as heat treatment and plating. The PPAP manual lists a change of supplier as its own notification trigger.
- Method. The same work instruction on a new layout, with new material flow and often a new language.
- Measurement. New or moved gauges, new appraisers, a new lab.
Adapt the Mother Plant’s PFMEA
Start from the mother plant’s approved PFMEA, mark every difference and re-rate what the differences touch.
- Process flow first. Draw it for the new layout, then map each operation from old to new: same, changed, new or removed.
- Mark the differences. For each changed or new operation, list what differs under the 6 headings above.
- Severity. It usually carries over: the product and the end user did not change. Check the effects on your own plant and the ship-to plant.
- Occurrence. Re-rate every row whose prevention control or machine changed. The mother plant’s history does not cover a machine it never ran.
- Detection. Re-rate every row whose gauge, test or inspection changed, on the new gauge after its study.
- Action Priority. Re-score with the Action Priority calculator and take every High row to the team.
Carry the Mother Plant’s Lessons
Every 8D, complaint and scrap cause the mother plant learned from belongs in the new PFMEA before trial runs start.
- Pull the history. 8Ds, customer complaints, nonconformance reports and scrap causes for the part and its process.
- Move the fixes, not only the rows. Each root cause should be a row and each fix a control on the new line. An error-proofing device added after an 8D at the mother plant has to exist at the new plant, or the failure comes back.
- Ask the people. Before the move, sit with the mother plant’s operators and setters. The adjustments they make by feel belong in the PFMEA or the work instruction.
Moving a line to a new plant?
Get the PFMEA transfer checklist: what changes at the new site and what your customer has to approve.
We email you the PDF. No newsletter. Privacy policy
The Control Plan and Gauges at the New Site
Build the new control plan from the new PFMEA. Do not copy the mother plant’s control plan.
- Every line from a row. Each detection control in the new PFMEA has a control plan line, and each special characteristic has a reaction plan.
- Every gauge studied. Plan an MSA study at the new site for every gauge the control plan names. A measurement system is the gauge plus the people, the method and the room around it.
- Backup methods approved. If a gauge or error-proofing device is not ready, the alternate method falls under IATF 16949 clause 8.5.6.1.1. It must be approved, referenced in the control plan and reviewed daily, with customer approval where required.
- Work instructions rewritten for the new layout, in the operators’ language.
The PPAP Plan
Plan the PPAP at the new site like a launch. Reuse only what your customer agrees can carry over.
- The run. A production run at the new site, on the new or moved equipment, with the new operators, at rate. The AIAG default is 1 to 8 hours of production and at least 300 consecutive parts, unless the customer specifies otherwise.
- The studies. Dimensional results, MSA and capability from that run. The mother plant’s studies describe the mother plant.
- The documents. Process flow, PFMEA and control plan for the new site, with matching revisions. VDA 2 allows unchanged documents from an earlier approval to be referenced.
- The bank. Build enough parts at the old site to cover the move and the approval. Agree the quantity and the old line’s stop date with the customer.
What to Tell the Customer
Tell the customer before the move, in writing, and keep it informed until the new site is approved. Your SQE wants 5 lines:
- What moves, from where to where, and when.
- What changes and what does not: equipment, people, suppliers, measurement.
- The PPAP plan: level, elements, run date and submission date.
- How supply is protected: the bank and the old line’s stop date.
- Who owns the move, by name.
Do not promise a stop date for the old line before the new site has its approval.
How Tacit AI Approaches This
Tacit AI builds the PFMEA, control plan and equipment FMECA from your own process flows, drawings, manuals, 8Ds and failure reports, to AIAG-VDA and IEC 60812, with every row traced to its source. For a transfer, you start the new plant’s PFMEA from the mother plant’s with every difference visible. The mother plant’s 8Ds, complaints and NCRs are imported and linked to the rows they belong to.
The control plan is built from the PFMEA rows, and an alignment check flags every line that no longer matches. Work instructions are drafted from the control plan, with sign-off. Your engineers review and approve every change. It works on top of the FMEA tool you already run.
A Top 20 Global OEM builds FMEAs 8× faster with it, with 26% fewer actions after customer review.
If a line is moving, book a working session and bring the mother plant’s PFMEA and the new site’s equipment list. See also how to link 8Ds to the PFMEA and the control plan template.
Moving a line to a new plant?
Get the PFMEA transfer checklist: what changes at the new site and what your customer has to approve.
We email you the PDF. No newsletter. Privacy policy
Frequently Asked Questions
Does moving production to another plant require a new PPAP?
Expect it. The AIAG PPAP manual lists tooling and equipment moved to a different plant site as a change that needs customer notification. Get the PPAP level and the elements in writing.
Can we copy the PFMEA from the mother plant?
Use it as the start, not the answer. Review every operation for changes in equipment, people, material, environment, method and measurement, and re-rate what changed.
Does IATF 16949 require a trial run for a change of production location?
Clause 8.5.6.1 says changes such as a new manufacturing location should require a production trial run. When the customer requires it, you also notify it and get documented approval before the change.
Do we need to tell our IATF certification body?
Yes. Under the IATF Rules 6th edition you notify it of any relocation. It decides between an initial audit, a special audit or added time at the next audit.