On New Business Hold: The Supplier Recovery Plan

Tacit AI · · 8 min read
LinkedIn

Purchasing has told you that your company is on new business hold with a major customer. The parts you ship today keep shipping. The next programs are sourced without you. The CEO wants to know what it costs and how long it lasts. Each plant manager wants to know what changes on the floor.

This guide is for the VP Quality or the general manager of the business unit who owns the recovery. It covers what a hold means at the large OEMs, why only a systemic fix lifts it, a 90-day plan, and what to tell the CEO and the customer.

The short version

  • Get the reasons for the hold and the release criteria in writing.
  • Name 1 executive owner, hold 1 weekly review and keep 1 tracker the customer can see.
  • Fix the system: every plant’s FMEAs and control plans, not only the part that failed.
  • Carry each lesson to every plant that runs the same process, and keep the proof.
  • Ask for a release review only when the evidence shows the fix holds.

What a New Business Hold Means

A new business hold makes you ineligible for new work with that customer until it lifts the hold. When quality is the reason, it is a judgment on your quality system, not on 1 part. Each OEM runs its own version.

  • GM. Its customer-specific requirements for IATF 16949 call New Business Hold a special status. GM notifies the supplier and can file an IATF performance complaint based on the issues behind it. That complaint follows the IATF certificate decertification process.
  • Ford. As Crain’s Detroit Business reported in May 2026, Ford is putting suppliers that keep missing quality targets on a no-bid list for new programs (via Ford Authority).
  • Stellantis. Like GM and Ford, it applies the red-supplier process. A red status on its scorecard can lead to a performance complaint, a special audit and a major nonconformity against IATF 16949 clause 9.1.2.1, as Bureau Veritas explains.

The common point: the problems behind a hold can reach your IATF certificate. Names and rules differ by customer. Get the reasons, the release criteria and the name of the person who decides, in writing.

Why Only a Systemic Fix Lifts It

The customer put the hold on the company, not on a part number. It lifts the hold when it sees that the system that let the problems through has changed.

  • Customers count repeats across sites. PACCAR’s supplier manual, for example, treats the same root cause on any part from any of the supplier’s locations, within 2 years, as a repeat.
  • The IATF rules ask the same. A root cause analysis for your certification body must consider the cause’s impact on other processes and products.
  • 1 fixed part proves 1 fix. The customer needs proof that your FMEAs, control plans and lessons learned work across the business.

On new business hold?

Get the 90-day recovery plan outline: governance, every plant’s FMEAs and control plans, and the evidence your customer will audit.

We email you the PDF. No newsletter. Privacy policy

Days 1 to 15: Set Up the Recovery

Run the recovery like a launch: 1 owner, 1 plan, 1 weekly review. The customer should see the same plan you run.

  • Executive owner. The general manager or the VP Quality, with the authority to move people between plants.
  • Weekly steering. Plant managers, quality, engineering and purchasing. Same hour every week, decisions in writing.
  • 1 tracker. Every open issue at every plant, with owner, date and status. Share it with the customer’s supplier quality team.
  • The baseline. Every open complaint, 8D, controlled shipping case and audit finding, by plant and by customer.
  • Containment first. Confirm every open issue is contained before the fixes start.

Days 16 to 30: Find the System Cause

Group the failures by cause, not by part number. The pattern shows where the system broke.

  • Risk analysis. If no PFMEA row named the cause, the risk analysis missed it.
  • The chain. A PFMEA control that never reached the control plan is a broken link.
  • Lessons learned. The same cause at 2 plants means the lesson stopped at the 1st.
  • Design. A characteristic never marked as special, or a design change the PFMEA never saw.
  • Equipment. Worn tooling or a drifting process that no maintenance task covered.

Days 31 to 60: Fix Every Plant’s FMEAs and Control Plans

Fix the chain at every plant that runs the affected process, starting with the plants behind the hold. A fix at 1 plant leaves the gap open at the others.

  • Start from the master. Fix the master PFMEA first, then every plant FMEA derived from it.
  • Rebuild the control plan from the PFMEA. Every detection control gets a control plan line. Every special characteristic gets a reaction plan.
  • Bring in the 8Ds. Every complaint and 8D since the last review lands in the row it belongs to.

Days 61 to 75: Carry Lessons Learned Across Plants

Turn every cause you found into a check for each plant with the same process, machine or material. Then record what each plant found.

  • 1 lesson per cause, written as a check another plant can run in a day.
  • Each plant answers: applies or not, found or not, fixed by when.
  • Each lesson goes into the risk analysis. IATF 16949 clause 6.1.2.1 asks for lessons learned from recalls, field returns, complaints, scrap and rework.
  • Add each lesson to the master FMEA, where the next program starts.

Days 76 to 90: Build Evidence the Customer Can Audit

Build the evidence the customer will sample before you ask for a review. Assume it picks the plant and the part.

  • Closed corrective actions with effectiveness data, not only closure dates.
  • Revised FMEAs and control plans at every affected plant, with matching revisions.
  • The lessons learned log, with each plant’s answer.
  • Internal audits of the changed processes by people outside the team.
  • The customer’s scorecard trend since the hold started.

Then ask for the release review, with each criterion and its evidence side by side.

What to Tell the CEO and the Customer

The CEO wants 3 answers: what the hold costs, what the plan is, and when the customer will review it. Do not guess the cost. List the quotes and programs you cannot bid for with this customer, from purchasing’s records, and the recovery spend to date.

The customer wants 4 lines: what failed, why the system let it through, what changed across the business, and the evidence. Send them on the same day each week. Ask for the release review only when every criterion has evidence behind it.

How Tacit AI Approaches This

Tacit AI builds the full DFMEA, PFMEA, control plan and FMECA from your own documents and data, to AIAG-VDA and IEC 60812, with every row traced to its source. An engineer approves a fix once and it reaches the master FMEA and every derived project, part and plant FMEA. It imports 8Ds, complaints, NCRs and warranty claims and links each record to the FMEA row it belongs to. FMEA freshness flags rows whose evidence is out of date. It works on top of the FMEA tool you already run, in your own cloud or a dedicated environment.

A Top 20 Global OEM builds FMEAs 8× faster with it, with 26% fewer actions after customer review. 100,000+ FMEA rows built.

If your company is on new business hold, book a working session and bring 1 master PFMEA, 1 derived plant PFMEA and the 8Ds behind the hold. See also how to get out of controlled shipping and how to close an IATF major on your FMEA.

On new business hold?

Get the 90-day recovery plan outline: governance, every plant’s FMEAs and control plans, and the evidence your customer will audit.

We email you the PDF. No newsletter. Privacy policy

Frequently Asked Questions

What does new business hold mean for a supplier?

You are not eligible for new business with that customer until it lifts the hold. It does not by itself stop the parts you ship today. The customer sets the release criteria.

How long does a new business hold last?

Until the customer sees evidence that your system has changed. There is no standard duration. Agree the release criteria and the review dates in writing at the start.

Can a new business hold affect our IATF 16949 certificate?

Yes. GM can file an IATF performance complaint based on the issues behind a hold. A performance complaint starts your certification body’s decertification process, which can bring a special audit and a suspended certificate.

What is the difference between controlled shipping and new business hold?

Controlled shipping adds inspection to protect the customer from 1 problem. A new business hold is a sourcing decision about your whole company. A supplier that keeps failing in controlled shipping can be escalated toward a hold.

What evidence lifts a new business hold?

Proof that the fix works across the business: corrective actions with effectiveness data, updated FMEAs and control plans at every affected plant, and lessons carried to similar processes. The customer decides what counts. Ask for its list on day 1.



Bring one FMEA.
See what it’s missing.

Your engineers judge the output. 30 minutes.

Cookie settings
Necessary cookies keep the site working and are always on. Analytics and advertising cookies are only set if you allow them. You can change this at any time. Privacy policy
Necessary
Allow Necessary cookies.
Analytics
Allow Analytics cookies.
Advertising
Allow Advertising cookies.